伊春变压器的安装

发布者:伊春变压器厂    发布时间:2018-07-24
伊春变压器的安装
安装前的准备工作
    1)选择安装前伊春变压器及其组件的存放方式和地点。
    2)确定伊春变压器卸车和移到安装位置的方法。
    3)选择所需伊春变压器油的型号、数量及准备方法。
    4)制定人员组织措施和工作安全措施,制定必要的安全防火措施。
    5)准备起吊和工艺设备、工器具及辅助材料。
    6)准备安装和验收工作所必需的技术文件。
 
安装时的安全措施
1)安装伊春变压器时,应设一名具有工作经验的专业技术人员负责安全技术。检查设备机器、机构、辅助设备和工器具是否良好及使用是否正确;检查工作现场所设的安全技术措施是否合理,有无危及人身和设备的杂物。保证焊接工作场所以及保证有安全放置易燃材料的地方.现场应备有防火器材。必要时应设警告牌。
    2)严格遵守DL408-1991《电业安全工作规程》,现场有足够的安全技术措施和组织措施。
 
安装的收尾工作
    伊春变压器安装后油箱一侧的滚轮下面垫上金属块,使其装气体继伊春变压器侧向往上倾斜。对伊春变压器,在设备就位后,应注意一、二次引线是否符合技术要求,是否满足其安全距离,工作现场有无遗留危及投入运行的设备和杂物,是否已清理等。
 
Installation of distribution transformers
 
Before You Install
    1) Select to install the transformer and its components before storage methods and locations.
    2) Determine the transformer to unload and move to the installation location.
    3) Select the type, quantity and preparation of the required transformer oil.
    4) develop a staff organizational measures and safety at work measures, to develop the necessary fire safety measures.
    5) Prepare the lifting and process equipment, industrial equipment and auxiliary materials.
6) Prepare the necessary technical documents in the installation and acceptance work.
 
Installation of security measures
1) installation of transformers, should set up a work experience professional and technical personnel responsible for security technology. Check the equipment and machinery, institutions, auxiliary equipment and industrial equipment are good and use correctly; check the work site safety measures reasonable, with or without endangering personal and equipment debris. To ensure that the welding in the workplace and to ensure a safe place flammable materials. Site should be equipped with fire-fighting equipment. Necessary, set up warning signs.
    2) strict compliance with the DL408-1991 "Electrical safety at work regulations, the site have adequate security measures and organizational measures.
 
Installation of finishing work
    Below the tank side of the wheel after installation of the transformer mat piece of metal up so that the relay mounted gas lateral tilt. Distribution transformers, the device in place, should pay attention to a secondary lead meets the technical requirements to meet its safe distance, whether the work site legacy endanger the operational equipment and debris, whether cleared.

快速通道

手机:

+131-8108-9999

座机:

+0635-8783-999

传真:

+0635-6066-688

邮箱:

858033047@qq.com

版权所有 ©  伊春变压器,伊春变压器厂,伊春中能变压器厂
电话:0635-6066688  8783999 传真:0635-6066688  手机:13181089999  联系人:陈经理
邮箱:858033047@qq.com  QQ:858033047  鲁ICP备18003380号-2
技术支持:互联纵横

中能变压器二维码微信客服